The ideal schedule is dynamic and allows the logic to drive the forecast dates. Hard Constraints FilterĪ quality project schedule avoids hard constraints. It strips out all the summary and milestone tasks so you can focus on the key tasks that represent the project schedule. This filter will display all the incompleted tasks at the lowest level of the work breakdown structure. Add And Baseline Duration does not equal 0d.Select View – Filters – New Filter (Figure 1).I’m accessing all the filters using the View – Filters tab in MS Project 2013. By using the Incomplete Tasks filter, I can quickly identify tasks that need to be updated by the project team. Summary, subprojects, milestone and tasks missing baselines are not evaluated. In this filter, I only want to review tasks at the lowest level of the work breakdown structure and identify the incomplete tasks.